May 2009

  • 1
  • 2

Challenges of Stream Restoration as a Stormwater Management Tool

Part 1: A designer's perspective

Article Tools

Create a Link to this Article
small stream

Photo: City of Charlotte Figure 1. Storms caused bank failures along this small stream, Hope Park Branch.

Additional Article Content

By Joshua B. Gilman, Jarrod Karl

1 Comments

As the first of a three-part series on stream restoration intended to realize the disparity between design and construction, and how this contributes to failure, this article provides the designer’s perspective on which challenges pose the greatest risk to the success of a stream restoration project.

Restoration may be defined as the return of natural function lost, usually resulting from associated watershed management such as development and agricultural practices. Depending on the number of lost functions restored, or the level of improvement, restoration may also take the simpler form of rehabilitation or stabilization. Restoration, rehabilitation, and stabilization of streams are performed for a variety of reasons. The primary driver for this type of work is the Clean Water Act (CWA). The objective of the CWA is “to restore and maintain the chemical, physical, and biological integrity of the nation’s waters,” and, for this reason, it prohibits the discharge of dredged or fill material into wetlands, streams, and other waters of the United States, unless a permit issued by the US Army Corps of Engineers or approved state under CWA Section 404 authorizes such a discharge.

Under the CWA, there are two major mechanisms that promote improved stream health: 1) Section 404 of the CWA, which provides for the use of compensatory mitigation to offset unavoidable damage to wetlands and other aquatic resources, and 2) the National Pollutant Discharge Elimination System (NPDES) stormwater permit program, which establishes requirements for municipal separate storm sewer system (MS4) nonpoint discharge. Permitted jurisdictions are sometimes prompted to perform watershed improvements, including stream and wetland restoration, as part of a larger strategy to implement total maximum daily loads (TMDLs).

Stability Versus Instability
Characteristic of most natural systems that reflect landscape conditions, stable streams exist in a state of dynamic equilibrium (Strahler 1957 and Hack 1960). This refers to an open system that, despite continuously receiving a varying inflow of discharge or sediment, maintains a stable hydraulic geometry (cross-sectional dimension, horizontal alignment [pattern], and vertical alignment [profile]) by transporting portions of this material within and beyond a mensurable reach. One fundamental axiom of stability is that the channel form is largely a function of the physics between discharge and the ability of a stream to move sediment, resulting in a equilibrium relationship, Qsds ~ QwS0 (Lane 1955), where Qs represents sediment quantity for a given discharge Qw, and where ds serves as the associated sediment size characterization (often the mean particle size, d50), and where S0 is the stream slope. If any of the four variables are changed, then changes to one or more of the other variables will occur to restore equilibrium. More simply, the channel form is a function of channel hydraulics, which in turn is a function of channel form.

Typically, restoration sites reflect the disequilibrium of a rapidly changing watershed, and active efforts to restore the channel form directly yield impacts (intentional or sometimes inadvertent) to the channel hydraulics and ability to transport sediment. This simplified relationship becomes more complicated when we attempt to account for the effect of vegetation. Regardless of attempts by engineers to accurately predict channel response following the construction phase of a restoration project, it is not unusual for the stream to experience unanticipated minor adjustments such as deposition on the inside of point bars or minor scour in areas of structure placement. The vulnerability of a restoration project is usually at its highest immediately following construction, and despite probability, that is usually when the stream will experience a major storm event and an increased likelihood of failure. Failures are often accompanied by cost overruns and adverse generalizations compounding the difficulty of advocacy.

A failure may be defined as the inability either to perform primary project objectives (i.e., bank stabilization, water-quality improvements, riparian and aquatic habitat enhancements) or to otherwise avoid creating additional impacts that result in unstable geometry attributable to one or more typical problems. Typical problems may include, but are not limited to, increasing velocity and/or shear stress resulting in excess competency and bank/bed scour; decreasing energy slope and channel depth resulting in reduced capacity and excess aggradation; and failure to account for multidimensional flow properties, such as lateral and vertical turbulence resulting in bank/bed armor structural instability. Failures may occur within an actively restored reach or throughout nearby upstream and downstream reaches, and they may take on a number of forms. While some failures may be immediately visible, others can take years to mature into potentially fatal conditions.

Why Failures Occur
Once a failure is recognized, the cause should be identified before attempting to correct the problem. This can often be a difficult process, as the designer and contractor have varying perspectives, and the client is pulled by strong arguments that attempt to divert fault. In many instances, the failure is a function of both the design and construction, and discerning accountability becomes a fruitless effort. Progress toward resolution begins only after the all parties involved come to realize the benefit of collaborative problem solving.

Design Errors
Design failures may occur at any point during a project process, from poor selection of a treatment site to poor design philosophy/methodology, incomplete construction documents, and weak implementation.

Photo: City of Charlotte
Figure 2. Before restoration, jute matting served as the only bank protection.

Early in the design process, one common error is the failure to establish practical project expectation (i.e., to identify the balance between project objectives and site potential). Before an appropriate site is selected and associated restorative treatments are prescribed, the project objectives should be clearly in alignment with the site potential. For example, attempting to achieve significant water-quality improvement along a single 500-linear-foot reach of highly urbanized stream channel is doomed from the start. Although the cumulative effect of multiple efforts such as this may be significant, the value of the single project may not be, cost-wise, beneficial. However, project objectives that better match the potential for such a site may include reducing a quantifiable source of sediment. Although stabilizing actively scouring banks with armor and bioengineering techniques may not eliminate erosive forces, such treatments may minimize the bank erodibility and be the most effective “fix” in terms of cost and schedule. This level of stabilization may not be considered restoration and will not correct the hydraulics, but will rather accommodate the current problem. Sometimes the momentum and excitement of performing stream restoration distracts stakeholders from realizing that the best means for achieving the desired level of water-quality improvement may not be practical or achievable by addressing a single site, and that retrofitting or implementing new best management practices (structural or nonstructural) elsewhere in the watershed may achieve desired results.

Beyond site selection, common stream restoration design failures include those associated with the quality of design documents. Acting in concert with stormwater interests, the stream mitigation elements of the Clean Water Act have stimulated the science and permitting industry, resulting in non-engineered design. While in many states, the application of engineering principles (hydrology, hydraulics, fluid/soil mechanics, surveying, etc.) is reserved for the licensed professional engineer, other states have allowed these practices to occur unregulated. Some design failures are attributable to the learning environment of this “emerging science” and attempts to stretch application in the interest of gaining knowledge. While this may be valuable to the industry, it may not always meet the need or budget of the municipal client. It should be noted that because of the complexity of working with dynamic systems driven by unregulated forces, a qualified design team incorporates various expertise, including those with foundations in science, engineering, and public policy. However, the actual design and accountability of proposing large-scale earthwork (plans, specifications, contract documents, etc.) should lie on the shoulders of the licensed engineer. Because of this “pioneering” nature of stream restoration, inconsistencies in design and individual designer standards have yielded mixed results when applied to conventional construction settings. Next Page >

  • 1
  • 2

What Do You Think?

Post a Comment

Brant D. Keller PhD

April 22nd, 2009 9:58 AM PT

Your experience is exactly correct in assessing stream bank restoration. The City of Griffin has conducted base line geomorphology on all it's watersheds to get a better understanding how to address existing conditions as well as previous issues. This year we will develop an assimulation tool which takes into consideration historcial , present and future land uses as a tool to consider the BMP's for loadings and design of the restoration.

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Stormwater E-mail Updates!

Get weekly news and updates through our Stormwater e-mail newsletter!